I'm replacing my 50 amp Dolphin charger with a 100 amp Dolphin charger. The larger charger requires larger cables. Past posts have addressed the issue and no one
has come up with a suggestion on running new cables through the present cable duct which is filled with some very hard material. I would like to hear form anyone who has attempted rerunning cables through the existing ducting. Bill Reynolds Cloudstreet
|
|
Chris Doucette
You can drill new holes above them through the bulkhead there’s an area in front of the tank that small just above where the cables penetrate right Within the foot step.
toggle quoted messageShow quoted text
Make sure you know we are drilling as not to drill into the fuel tank.
On Jun 12, 2021, at 11:52 AM, william reynolds <sail23692@...> wrote:
|
|
As long as you drill through vertically above the existing cables in the cable way, you will miss the fuel tank.
I know, I've done it. Cheers Alan Elyse SM437
|
|
Take pictures when you do it!
-- Jason Rutledge SV Liahona SM 335
|
|
Bill,
Two years ago, I replaced my chargers for Mastervolt 60 amp and 100 amp. According to the specs for the 100 am charger a cable AWG2 is perfectly fine and thus it can be connected to the batteries with the standard cables of our boat. I would not spend the effort changing them. If you want to add extra safety you can connect in parallel the cables going for each of the two battery chargers. I kept the same cables of the original 30 and 60 amp charger cables for the 60 and 100 amp chargers without any problem. Jose Ipanema SM 276
|
|
Bill Kinney
If you drill holes here, be sure to figure out how you are going to make them waterproof after running the cables. This is one of the watertight bulkheads that is critical to making an Amel, an Amel. The engine room is by far the most likely place to have water entering the boat in an unplanned manner. That is a big enough problem, but having holes which allow that problem to spread unchecked to the rest of the hull has the potential to turn a big problem into a disaster.
|
|